Published: 10 August 2022

ESCC will be carrying out carriageway patching works on the B2116 Keymer Road/Lewes Road/Ditchling Road.

Works will start on Tuesday 30 August and continue until Thursday 15 September.

The B2116 will be closed in sections (detailed below) between 7pm and 6am each night. There will be no weekend working.

Phase one - 30 August: from Beacon Hurst to The Drove.
Phase two - 31 August – 1 September: B2112/B2116 from South Street to Underhill Lane.
Phase three - 2 & 5 September: Underhill Lane to Streat Lane.
Phase four - 6– 7 September: Streat Lane to Plumpton Lane.
Phase five - 8- 12 September: Plumpton Lane to Allington Lane.
Phase six - 13 -15 September: Allington Lane to A275 Offham.

A suitable diversion route will be signed on site for each phase.

Please also see our website for information about this work: https://www.eastsussexhighways.com/highway-schemes/b2116-ditchling-to-offham